Are You Planning To Build? – Take Great Care


I have come across many sad cases over the years of honest people who are building their dream home only to find that the builder has scarpered, the money has run out and there is a distinct dearth of windows and doors, electrical wiring is nowhere to be seen and there is some really effective ventilation where the roof should be.

Enquiries follow only to reveal that the 8 teams of workers that came and went over the 14 months the project dragged on for left because they hadn’t been paid. Sadly pleonexia is alive and well in the construction industry and contractors know that the average owner builder, Mr and Mrs Nicefriendlypeople, are easy prey for their games. Lambs to the slaughter comes to mind.

Such cases are common in Bali and inevitably the “builder” has been paid more than the work he has completed. He will have worked out that by running off now he will end up with more profit than if he finishes the project and he will avoid the most difficult period when he is doing the finishing work and trying to get final payment.

Sometimes he may add insult to injury by demanding even more money, his argument being that the money paid is less than the amount of work completed.

When a contractor walks away from a half finished job it leaves all sorts of problems. The project is likely to be considerably delayed and it may be difficult to find a new contractor willing to take on the mess that someone else has left. Unfortunately the sort of contractor who perhaps had planned all along to walk away from a half finished job may well be the sort of person that will have also cut corners in the work.

 

So how do we protect ourselves?

We use standardized systems that; if well set up, properly thought out and a rigidly applied; minimise the risks involved and keeps contractors in check. These systems use a Bill Of Quantities and a Schedule of Payments.

A good Project Manager can set up and manage these systems for you.

 

Bill Of Quantities

A Bill of Quantities (or BoQ) is a detailed list of all the tasks that have to be completed to construct the project. Each part of the work is fully described and costed so everyone knows exactly what is to be done and how much it will cost.

Let us look at a typical Bill Of Quantities and see what information and the level of detail you should expect. On the website at www.mrfixitbali.com/images/sampleprogressreport.pdf you will see a sample report from a database designed for managing project progress and payments.

The Bill Of Quantities is broken down into headings for each section of the work such as:

  • Site clearing and project setup
  • Foundations
  • Structure
  • Floor slabs
  • Walls
  • Roof and ceilings
  • Windows and doors
  • Electrical Installation
  • Plumbing Installation
  • Ceramic wall and floor tiling
  • Painting
  • Drainage
  • Water Supply

 

We also need to add on:

  • Architect’s Fees (10%?)
  • Structural Engineers Fees
  • Construction Tax (10%)
  • Legal costs (IMB, contract fee, etc)

Under each of these headings will be a breakdown of the tasks within that heading with the estimated costs. The tasks should describe the work to be done, the type or level of quality of the materials to be used and a quantity such as cubic meters (excavation, fill or concrete), square meters (tiling, roofing and painting) or per item (washbasins, toilets, doorhandles, stress pills, etc.). The price for a single unit and the total price for the totals needed for the project is also given. The description also should, where relevant cross refer back to the drawings in order to tie the specifications stated on the drawings as part of this document. This provides legal protection. The costs are totalled up to give us the TOTAL cost of the project.

Alright so we now have our Bill of Quantities and this should become a part of the legal documentation that becomes part of the building contract. The builder must sign up to agree to construct according to this document. You might want to add a penalty clause should he not complete the contract, if he refuses such a clause this might ring warning bells.

 

The Schedule of Payments

Now we come to the important part, we have to determine a schedule of payments. We start by saying we’ll give you so much to get started. This gives the contractor some cash to pay for some materials and start up costs.

Next we have to work out how we will carry on paying as the project proceeds. We have to make sure the contractor has enough money to carry on working but also make sure that if he heads for the hills we are not out of pocket. This might sound difficult but remember there is a profit margin for the contractor in each part of the project and we can use the profit margin on the work he has already completed as the advance for the cost he will incur on the next part. This means that after each payment is made you and the contractor are square, you have the work completed and he has his profit so far.

It is advisable to avoid paying large amounts. If you have only 3 or 4 payments for the whole project the amount paid and the amount of project completion will vary to a far greater degree than if you use smaller, more frequent payments.

Construction companies tend to use a more rigid approach. They will set milestones and pay only when the milestone is achieved. For example they may only pay for the roof when every part of the roof is completed and has been inspected and passed.

Ok now the final stage is to manage the Payment Process. Before any payment is made the project is inspected and payment made according to the actual work done. You will need an engineer to go through the bill of quantities and check each line item to assess the percentage of completion. This is totalled up to give you the total financial value of the construction that has been completed.

If you look at the sample file you will see that there is a column second from the right with the percentage complete entered which is then calculated into a monetary value for the amount of work completed in the right hand column. Armed with this information, some common sense and a healthy dose of assertiveness, you can now make sure you are not paying more than you should.

A good contractor will understand all this. He/she will give you a detailed Bill of Quantities and will respect your desire to get progress inspections carried out before you release money.

If you know you are not a very assertive person beware that the contractor may sense this and feel that he can exploit you. It might be best to find someone to represent you in dealing with making payments but make sure it is someone you trust.

Look out for tell tale signs of dodgy dealings. Don’t let emotions take over, be methodical and never assume the contractor is your best friend and is going to be benevolent to you. Keep an eye out for vagueness or lack of detail in the Bill of Quantities. Excuses should ring alarm bells. If he cannot keep his workers this suggests there is a problem. If the staff walk off find out why and if they have not been paid you can bet your life the contractor will be dishonest with you. It is also well to remember that happy workers will do better work than unhappy workers.

Protection comes from having aclear definition of what is to be done, what has been done and accurate costings for the two.

 